QUANGANHCONS | INDUSTRIAL EPC ENGINEERING
Industrial rooftop PV 750 kWp: equipment and EPC reference
A structured technical reference for factories evaluating rooftop PV, site electrical interfaces and EPC budgets.
QAC-SOL-EST-20261109-14EF1751 · QAC Solar 8.21.0
1. Applications and self-consumption
Several 125 kW inverters require AC collector-board zoning, route loss assessment, switchboard fault-duty checks and zero-export measurement at the correct PCC. The system is a grid-connected self-consumption PV reference, excluding battery storage; it is not evidence of a completed installation.
2. Equipment nameplate and electrical configuration
| Capacity class | 750 kWp |
|---|---|
| PV modules | 1,172 × LONGi Solar LR7-72HVH-640M, 640 Wp |
| Installed DC power | 750.08 kWp |
| Inverters | 6 × Sungrow SG125CX-P2 |
| Combined AC rating | 750 kW |
| PV strings | 66, subject to MPPT allocation checks |
| DC/AC ratio | 1 |
| Reference | QAC-SOL-EST-20261109-14EF1751 · 09 Nov 2026 |
3. Engineering calculations
PDC = 1,172 × 640/1,000 = 750.08 kWp. DC/AC ratio = 750.08/750 = 1. PV output and clipping depend on inverter model, MPPT assignment, module temperature and irradiance.
At 400 V three phase and assumed power factor 0.99, aggregate AC current is 750 × 1,000/(√3 × 400 × 0.99) ≈ 1,093.47 A. This is a mathematical aggregate, not a one-feeder design. Calculate protective device ratings, cable ampacity, voltage drop and prospective fault level separately for each AC section and PCC.
4. Roof, protection and grid interface
Several 125 kW inverters require AC collector-board zoning, route loss assessment, switchboard fault-duty checks and zero-export measurement at the correct PCC. The system is a grid-connected self-consumption PV reference, excluding battery storage; it is not evidence of a completed installation.
5. Programme and acceptance
Survey and SLD approval → material procurement → safe installation of mounting and PV DC/AC circuits → protection/earthing/insulation tests → commissioning and as-built documentation. Project duration, utility requirements and exclusions will be confirmed after survey.
Indicative WBS/Gantt (no fixed dates)
6. 750 kWp Solar estimate — view and download
Quote reference: QAC-SOL-EST-20261109-14EF1751 · QAC Solar 8.21.0 · Pre-survey reference
Before VAT: 9,000,960,000 đ · Illustrative VAT 10%: 900,096,000 đ · With VAT: 9,901,056,000 đ
Open PDF separately if mobile preview is blocked.
Preview matching source-locked PDF below. This is a preliminary budget; unit prices can be rounded and the actual utility/MV scope requires independent verification.
7. 12-month production and a representative 24-hour day
Example only, not surveyed production or measured load: PVGIS 5.3/ERA5 2023 HCMC (10.8231,106.6297), 10° south-facing, PVGIS loss 14% once, AC limits applied per configuration. Hypothetical factory operates Mon–Sat: 75% AC daytime load, 50% lunch, 35% evening, 18% overnight/Sundays; zero export assumed.

| Month | PV kWh | Self-use kWh | Curtailed kWh | Load kWh |
|---|---|---|---|---|
| 1 | 77,988 | 70,651 | 7,338 | 225,240 |
| 2 | 90,286 | 80,338 | 9,948 | 205,920 |
| 3 | 105,250 | 94,448 | 10,801 | 230,040 |
| 4 | 95,330 | 85,058 | 10,273 | 217,200 |
| 5 | 88,368 | 82,692 | 5,675 | 230,040 |
| 6 | 76,823 | 71,658 | 5,166 | 222,000 |
| 7 | 72,134 | 67,774 | 4,360 | 225,240 |
| 8 | 89,496 | 82,531 | 6,965 | 230,040 |
| 9 | 72,762 | 68,722 | 4,040 | 222,000 |
| 10 | 80,187 | 73,381 | 6,805 | 225,240 |
| 11 | 78,944 | 71,973 | 6,971 | 222,000 |
| 12 | 86,314 | 79,037 | 7,277 | 225,240 |
Representative day: 15 Mar 2023

Show 24-hour loads and assumptions
| Hour ICT | PV kW | Load kW | Self-use kW |
|---|---|---|---|
| 0 | 0 | 135 | 0 |
| 1 | 0 | 135 | 0 |
| 2 | 0 | 135 | 0 |
| 3 | 0 | 135 | 0 |
| 4 | 0 | 135 | 0 |
| 5 | 0 | 135 | 0 |
| 6 | 22.8 | 135 | 22.8 |
| 7 | 168 | 337.5 | 168 |
| 8 | 303.6 | 562.5 | 303.6 |
| 9 | 426.6 | 562.5 | 426.6 |
| 10 | 490 | 562.5 | 490 |
| 11 | 519.3 | 562.5 | 519.3 |
| 12 | 513.9 | 375 | 375 |
| 13 | 327.5 | 562.5 | 327.5 |
| 14 | 283.3 | 562.5 | 283.3 |
| 15 | 214 | 562.5 | 214 |
| 16 | 126.3 | 562.5 | 126.3 |
| 17 | 28.8 | 562.5 | 28.8 |
| 18 | 0 | 262.5 | 0 |
| 19 | 0 | 262.5 | 0 |
| 20 | 0 | 262.5 | 0 |
| 21 | 0 | 262.5 | 0 |
| 22 | 0 | 135 | 0 |
| 23 | 0 | 135 | 0 |
JRC PVGIS 5.3 ERA5 2023 · QAC-SOLAR-INDUSTRIAL-HCM-2023-R1
8. Rooftop PV installation and equipment images
Images already in the QAC content library; not photographs of this exact system.



9. Standards, checkpoints and FAQ
Review IEC 62548-1, IEC 60364-7-712 and applicable Vietnamese electrical/fire/building requirements. PV module family reference: LONGi 640 Wp datasheet; verify the exact inverter datasheet and firmware.
Confirm MPPT and cold Voc/Isc, AC/DC SPD and selectivity, earthing, roof/wind, utility interface and fire safety before construction.
Is this a final turnkey MV EPC quotation?
No. Only the priced BOQ scope is included. MV collector, new substation and PCC upgrades must be validated separately.
10. Construction video and related solutions
Watch PV installation video on YouTube
Video reference only, not project-completion evidence.
Industrial rooftop solar · Solar estimate library · Substation services
11. Estimate another solar system
Choose Solar & storage for your property
From electricity needs to a preliminary system and budget. No contact details required.
Automatic pre-survey calculations
Enter your sizing input to see module area, access area, roof requirement, module mass, capacity and electrical configuration.
Developed and operated by QuangAnhcons. Preliminary results require site survey and written confirmation before ordering or construction.
Solar 8.21.0 · QAC-UI-QUOTE 1.1.1
© 2026 QUANG ANH CONSTRUCTION ELECTRICITY COMPANY LIMITED. Quotation prepared by QuangAnhcons. Please retain the issuer name and reference when saving or sharing. Third-party names and materials belong to their respective owners.
Tiếng Việt
简体中文
Deutsch
日本語
한국어
ไทย
Русский
Français