Industrial rooftop PV 10 MWp: equipment and EPC reference
A structured technical reference for factories evaluating rooftop PV, site electrical interfaces and EPC budgets.
QAC-SOL-EST-20261109-5A560DF4 · QAC Solar 8.21.0
1. Applications and self-consumption
This is a multi-block industrial-scale solar development. Engineering must include multiple step-up units, MV feeders, protection selectivity, SCADA/EMS, metering and the grid-interface scope; never one 400 V main board. This is a PV self-consumption reference without battery storage, not a surveyed or previously built project.
2. Equipment nameplate and electrical configuration
| Nominal capacity class | 10 MWp |
|---|---|
| PV module | 15,625 × LONGi Solar LR7-72HVH-640M, 640 Wp each |
| Installed DC | 10,000 kWp |
| Inverters | 67 × Sungrow SG125CX-P2 |
| Combined AC | 8,375 kW across 14 provisional groups |
| Strings | 869, with MPPT allocation requiring verification |
| DC/AC ratio | 1.19 |
| Common VI/EN budget reference | QAC-SOL-EST-20261109-5A560DF4 · 09 Nov 2026 |
3. Engineering calculations
PDC = 15,625 × 640 / 1,000 = 10,000 kWp. DC/AC = 10,000 / 8,375 = 1.19. Check module temperature, MPPT operating window, input currents, inverter derating, clipping and lightning protection on the actual topology.
Aggregate 400 V three-phase current at assumed PF 0.99 = 8,375 × 1,000/(√3 × 400 × 0.99) ≈ 12,210.38 A. This is not a permissible single-board design. It must be divided among real inverter feeders, protected collector boards and (where required) MV step-up sections.
4. Roof, protection and grid interface
Roof strength, wind anchoring, waterproofing, walkways, cable routes, fault-level study, feeder grading, protection relays, PCC metering, anti-islanding and zero-export controls need separate checks. The step-up stations, protected medium-voltage feeder network, remote control and utility interface have NOT been established by this LV-only snapshot.
5. Programme and acceptance
Prepare WBS: site survey and conceptual single-line diagram → engineering, utility and protection coordination → equipment procurement → phased safe PV installation → LV/MV and commissioning works where within contract → protection/insulation/earthing checks → as-built records and handover. Detailed durations depend on site, supplier lead time and approvals.
Indicative WBS/Gantt (no fixed dates)
6. 10 MWp Solar estimate — view and download
Quote reference: QAC-SOL-EST-20261109-5A560DF4 · QAC Solar 8.21.0 · Pre-survey reference
Before VAT: 120,000,000,000 đ · Illustrative VAT 10%: 12,000,000,000 đ · With VAT: 132,000,000,000 đ
Open PDF separately if mobile preview is blocked.
Preview matching source-locked PDF below. This is a preliminary budget; unit prices can be rounded and the actual utility/MV scope requires independent verification.
7. 12-month production and a representative 24-hour day
Example only, not surveyed production or measured load: PVGIS 5.3/ERA5 2023 HCMC (10.8231,106.6297), 10° south-facing, PVGIS loss 14% once, AC limits applied per configuration. Hypothetical factory operates Mon–Sat: 75% AC daytime load, 50% lunch, 35% evening, 18% overnight/Sundays; zero export assumed.

| Month | PV kWh | Self-use kWh | Curtailed kWh | Load kWh |
|---|---|---|---|---|
| 1 | 1,039,735 | 915,872 | 123,863 | 2,515,180 |
| 2 | 1,203,679 | 1,037,456 | 166,223 | 2,299,440 |
| 3 | 1,403,179 | 1,215,564 | 187,614 | 2,568,780 |
| 4 | 1,270,934 | 1,100,318 | 170,616 | 2,425,400 |
| 5 | 1,178,108 | 1,076,075 | 102,034 | 2,568,780 |
| 6 | 1,024,202 | 934,992 | 89,210 | 2,479,000 |
| 7 | 961,687 | 881,868 | 79,819 | 2,515,180 |
| 8 | 1,193,153 | 1,074,314 | 118,839 | 2,568,780 |
| 9 | 970,054 | 899,270 | 70,785 | 2,479,000 |
| 10 | 1,069,039 | 952,889 | 116,151 | 2,515,180 |
| 11 | 1,052,472 | 935,191 | 117,282 | 2,479,000 |
| 12 | 1,150,729 | 1,025,438 | 125,292 | 2,515,180 |
Representative day: 15 Mar 2023

Show 24-hour loads and assumptions
| Hour ICT | PV kW | Load kW | Self-use kW |
|---|---|---|---|
| 0 | 0 | 1,507.5 | 0 |
| 1 | 0 | 1,507.5 | 0 |
| 2 | 0 | 1,507.5 | 0 |
| 3 | 0 | 1,507.5 | 0 |
| 4 | 0 | 1,507.5 | 0 |
| 5 | 0 | 1,507.5 | 0 |
| 6 | 304.4 | 1,507.5 | 304.4 |
| 7 | 2,240.2 | 3,768.8 | 2,240.2 |
| 8 | 4,047.9 | 6,281.3 | 4,047.9 |
| 9 | 5,687.3 | 6,281.3 | 5,687.3 |
| 10 | 6,533 | 6,281.3 | 6,281.3 |
| 11 | 6,923.4 | 6,281.3 | 6,281.3 |
| 12 | 6,851.9 | 4,187.5 | 4,187.5 |
| 13 | 4,366 | 6,281.3 | 4,366 |
| 14 | 3,776.5 | 6,281.3 | 3,776.5 |
| 15 | 2,853.5 | 6,281.3 | 2,853.5 |
| 16 | 1,683.7 | 6,281.3 | 1,683.7 |
| 17 | 384.1 | 6,281.3 | 384.1 |
| 18 | 0 | 2,931.3 | 0 |
| 19 | 0 | 2,931.3 | 0 |
| 20 | 0 | 2,931.3 | 0 |
| 21 | 0 | 2,931.3 | 0 |
| 22 | 0 | 1,507.5 | 0 |
| 23 | 0 | 1,507.5 | 0 |
JRC PVGIS 5.3 ERA5 2023 · QAC-SOLAR-INDUSTRIAL-HCM-2023-R1
8. Rooftop PV installation and equipment images
Images already in the QAC content library; not photographs of this exact system.



9. Standards, checkpoints and FAQ
Assess IEC 62548-1, IEC 60364-7-712 and applicable Vietnamese electrical, structural, fire, and grid-connection rules. Module datasheet: LONGi LR7-72HVH. Inverter and relay selection must follow correct manufacturer revisions.
Confirm MPPT and cold Voc/Isc, AC/DC SPD and selectivity, earthing, roof/wind, utility interface and fire safety before construction.
Is this a final turnkey MV EPC quotation?
No. Only the priced BOQ scope is included. MV collector, new substation and PCC upgrades must be validated separately.
10. Construction video and related solutions
Watch PV installation video on YouTube
Video reference only, not project-completion evidence.
Industrial rooftop solar · Solar estimate library · Substation services
11. Estimate another solar system
Choose Solar & storage for your property
From electricity needs to a preliminary system and budget. No contact details required.
Automatic pre-survey calculations
Enter your sizing input to see module area, access area, roof requirement, module mass, capacity and electrical configuration.
Developed and operated by QuangAnhcons. Preliminary results require site survey and written confirmation before ordering or construction.