Reference configuration · 02 Nov 2026
100 kWp Solar: detailed estimate and schedule for factories and commercial buildings. Actual installed capacity is 100.48 kWp DC / 90 kW AC, comprising 157 LONGi Solar LR7-72HVH-640M modules and 3 Sungrow SG30CX-P2 inverters.
Three 30 kW inverters distribute power across AC branches. Check switchboard capacity, cable routes and control at the point of connection before finalising the design.
View and download the PDF / Excel estimateRequest a site-specific option
How is the 100 kWp configuration calculated?
The 100 kWp name is a reference capacity class. Actual DC capacity is module count multiplied by the exact model’s STC rating; AC capacity is the sum of inverter ratings. This pre-survey example is not assigned to a particular address or customer.
| PV modules | 157 × LONGi Solar LR7-72HVH-640M |
| Inverter | 3 × Sungrow SG30CX-P2 |
| DC/AC ratio | 1.116 |
| Electricity supply | 3-phase |
| Mounting arrangement | Cliplock metal roof, roof-following mounting; verify structure and connections on site |
| Module area | 424.09 m² |
| Assumed roof area | 605.84 m²; depends on roof coverage and clearances |
| Operating model | Grid-connected self-consumption; battery storage not included |
| Outage backup | A designed and tested backup-supply branch is not included |
Assumptions affecting quantities and design
- Roof elevation: 10 m. Ground-to-roof elevation; where no value is entered, the defaults are 4 m for a house, 10 m for a factory and 0 m for a yard. These are not standard building heights or frame elevations. Wind loads and lifting requirements need separate calculations.
- One-way DC route per string: 80 m. One-way route = roof elevation + horizontal run + roof run. Do not double it here; the two DC polarities are counted separately. Enter measured cable routes when available.
- Roof coverage factor: 70%. 70% is a preliminary layout scenario. It does not replace a layout, fire-safety clearances or shading analysis.
- Cold cell temperature: 0 °C. Confirm minimum cell temperature using site climate data and manufacturer instructions.
- Hot cell temperature: 70 °C. 70 °C is a scenario value. Cell temperature requires a model covering irradiance, wind and mounting conditions.
- AC-current allowance: 1.00 times. Use the manufacturer’s maximum AC current for Ib and follow its circuit-breaker instructions. Do not treat 1.25 as a universally mandatory IEC AC factor.
- Anchor spacing: 1.20 m. Material allowance only. Confirm wind loading, roof zones, purlin and anchor capacity, spans and the rail arrangement.
- Basic rail/clamp mass: 3 kg/m². Basic rails and clamps only; selected steel frames, reinforcement and bases are included separately in the weight check. Structural capacity has not been verified.
- Productivity factor: 85%. Productivity assumption for estimating crew size and duration; adjust it to the site and installation team.
View and download the estimate documents
Estimate QAC-SOL-EST-20261102-D8AA0A54 follows the QuangAnhcons form, with a watermark, detailed BOQ, commercial conditions, calculation annex and schedule. Download directly without entering an email address.
Download estimate PDFDownload Excel estimate
View the QuangAnhcons estimate documents
The embedded viewer preserves the document layout. On a phone, download the PDF or read the screen-friendly table below.
View the 100 kWp Solar EPC estimate PDF here
Open PDF full screen (if the viewer does not appear on your phone, open this link); the file can also be downloaded using the PDF button below.
Detailed 100 kWp estimate
Indicative total: VND 1,326,336,000
Unit selling prices and totals were exported from Solar estimator 8.21.0 on 02 Nov 2026 for this reference scope. VAT follows the estimate configuration. Transaction prices and taxes must be confirmed for the goods/services and contract date. This does not confirm that supplier purchase quotations remain valid.
On a phone, swipe horizontally within the table to see all columns: code, specification, unit, quantity, unit price and amount.
| Code | Item and specification | Unit | Quantity | Unit price (VND) | Amount (VND) |
|---|---|---|---|---|---|
| MAIN EQUIPMENT | |||||
| 1 | LONGi Solar LR7-72HVH-640M photovoltaic module640 Wp · 2382x1134x30mm | module | 157 | 2,831,738 | 444,582,866 |
| 2 | Sungrow SG30CX-P2 grid-connected inverter30 kW AC · 400 V · 3-phase · 3 MPPT | set | 3 | 41,319,254 | 123,957,762 |
| 3 | Sungrow Logger1000A/B data logger – preliminary selectionSungrow · Data acquisition and monitoring. Export-control capability depends on the confirmed configuration. | set | 1 | 22,016,099 | 22,016,099 |
| 4 | RS485 shielded twisted-pair cable, 2 × 0.75 mm² | m | 90 | 35,861 | 3,227,490 |
| 5 | RJ45 Cat6 UTP Ethernet patch lead, 1.5 m | piece | 2 | 95,246 | 190,492 |
| 139 | Bidirectional power meter/transducer at the point of connectionBidirectional power measurement for control at the point of connection. | piece | 1 | 7,208,142 | 7,208,142 |
| 140 | PCC metering CT/VT scope – voltage level and diagram require confirmationMetering scope. Confirm the CT/VT configuration against the approved diagram. | lot | 1 | 14,546,837 | 14,546,837 |
| 141 | Export-control integration and response/loss-of-signal testingExport-limiting integration and interlock testing to the confirmed design. | lot | 1 | 5,332,644 | 5,332,644 |
| 142 | Network infrastructure, auxiliary power and monitoring enclosure – scope to be finalisedAdditional monitoring infrastructure depends on the actual layout. Configuration requires confirmation. | lot | 1 | 4,790,918 | 4,790,918 |
| MOUNTING STRUCTURE / ALUMINIUM MATERIALS | |||||
| 6 | Standing-seam/cliplock roof clamps and fastening bolts | set | 332 | 29,920 | 9,933,440 |
| 7 | Extruded aluminium rail, 4.35 m longChiko | length | 88 | 400,145 | 35,212,760 |
| 8 | Aluminium rail splice with stainless-steel M8 bolts | set | 70 | 23,831 | 1,668,170 |
| 9 | Mid clamps for 30 mm module frames, including bolts, nuts and washersChiko | set | 296 | 14,318 | 4,238,128 |
| 10 | End clamps for 30 mm module frames, including bolts, nuts and washersChiko | set | 36 | 14,290 | 514,440 |
| 11 | Earthing clip for mid clampsChiko | set | 296 | 14,318 | 4,238,128 |
| 12 | Earthing conductor clamp with stainless-steel M8 boltChiko | set | 18 | 29,771 | 535,878 |
| 14 | DC cable clips suited to the outer diameter of 6 mm² PV cableChiko | set | 314 | 2,978 | 935,092 |
| DC CABLES / DC ACCESSORIES | |||||
| 17 | Solar DC cable, 6 mm², 1500 VDC – blackLeader DC-6-BK · Single-core PV cable; 1 core; 1,500 VDC; UV-resistant. | m | 720 | 30,330 | 21,837,600 |
| 18 | Solar DC cable, 6 mm², 1500 VDC – redLeader DC-6-RD · Single-core PV cable; 1 core; 1,500 VDC; UV-resistant. | m | 720 | 30,330 | 21,837,600 |
| 19 | DC connector pair matching the equipment manufacturer’s brand/seriesLeader · Connectors from a matching brand/series compatible with the equipment. | pair | 18 | 38,903 | 700,254 |
| 20 | Outdoor DC protective conduit – diameter and material to be selectedCVL | m | 144 | 13,346 | 1,921,824 |
| 21 | DC protective-conduit connector – to match conduit diameterCVL | set | 18 | 8,890 | 160,020 |
| 22 | Black UV-resistant cable ties, 5 × 200, pack of 500KST | pack | 1 | 66,669 | 66,669 |
| 23 | Black UV-resistant cable ties, 5 × 300, pack of 250KST | pack | 2 | 66,671 | 133,342 |
| AC SWITCHBOARDS / MSB BLOCKS / ACBs / MCCBs | |||||
| 26 | Solar enclosure – IP rating, Form and dimensions to be confirmedEnclosure only; circuit breakers and busbars are listed separately. | piece | 1 | 9,013,135 | 9,013,135 |
| 27 | Copper busbars, fabrication, N/PE supports and accessoriesCopper busbars, fabrication, supports and N/PE accessories. | assembly | 1 | 4,581,878 | 4,581,878 |
| 28 | Control fuses, 3 × 5 A, with holders | Set of 3 | 1 | 133,366 | 133,366 |
| 29 | R-Y-B phase indicator lamps | piece | 3 | 50,012 | 150,036 |
| 30 | AC collector-panel multifunction meter with kWh function – model to be confirmedSelec · Operational metering at the AC switchboard; it does not replace the control meter at the PCC. | piece | 1 | 3,912,670 | 3,912,670 |
| 32 | Solar MSB metering CT, 200/5 A, class 0.5SOmega CT-200/5A class 0.5S | piece | 3 | 389,602 | 1,168,806 |
| 33 | Switchboard auxiliary-circuit protection – rated current to be selectedOmega | piece | 1 | 1,001,572 | 1,001,572 |
| 34 | Switchboard temperature sensor | piece | 1 | 556,041 | 556,041 |
| 35 | Switchboard ventilation fan | piece | 2 | 1,338,925 | 2,677,850 |
| 36 | AC SPD – Type, Uc, Up, In/Imax and coordination to be confirmedHimel | set | 1 | 3,912,670 | 3,912,670 |
| 37 | Solar MSB main MCCB, 400 VAC, 160 AMitsubishi NF250-HV 3P 160A · Icu/Ics must suit the prospective short-circuit current at the installation point. | piece | 1 | 6,753,571 | 6,753,571 |
| 38 | Inverter-branch MCCB, 400 VAC, 63 AMitsubishi NF125-CV 3P 63A · Icu/Ics must suit the prospective short-circuit current at the installation point. | piece | 3 | 2,430,581 | 7,291,743 |
| LV AC CABLES / BUSDUCT / ACCESSORIES | |||||
| 39 | Inverter cable, CXV 4C-16 mm² (3P+N, separate PE)CADIVI · Cu/XLPE/PVC · 0.6/1 kV | m | 75 | 376,151 | 28,211,325 |
| 40 | Main cable, CXV 1C-70 mm², 1 parallel runs per phase and neutralCADIVI · Cu/XLPE/PVC · 0.6/1 kV | m | 140 | 351,873 | 49,262,220 |
| 41 | Main PE cable, CXV 1C-35 mm², 0.6/1 kVCADIVI · Cu/XLPE/PVC · 0.6/1 kV | m | 35 | 181,934 | 6,367,690 |
| 43 | Copper cable lug, 70 mm² – main cableCU-LUG-70 | piece | 8 | 38,896 | 311,168 |
| 44 | Cable-lug connection bolts – size to suit the equipment terminalsCadivi | set | 8 | 22,225 | 177,800 |
| 45 | Copper cable lug, 16 mm² – inverter phaseCU-LUG-16 | piece | 18 | 11,112 | 200,016 |
| 46 | Copper cable lug, 16 mm² – inverter PECU-LUG-16 | piece | 6 | 11,112 | 66,672 |
| 47 | 70 mm² cable-lug insulating boot – redCadivi BOOT-70 | piece | 2 | 6,667 | 13,334 |
| 48 | 70 mm² cable-lug insulating boot – blueCadivi BOOT-70 | piece | 2 | 6,667 | 13,334 |
| 49 | 70 mm² cable-lug insulating boot – yellowCadivi BOOT-70 | piece | 2 | 6,667 | 13,334 |
| 50 | Main neutral cable-lug insulating boot, 70 mm²Cadivi BOOT-70 | piece | 2 | 6,667 | 13,334 |
| 51 | 16 mm² cable-lug insulating boot – redCadivi BOOT-16 | piece | 6 | 6,669 | 40,014 |
| 52 | 16 mm² cable-lug insulating boot – blueCadivi BOOT-16 | piece | 6 | 6,667 | 40,002 |
| 53 | 16 mm² cable-lug insulating boot – yellowCadivi BOOT-16 | piece | 6 | 6,667 | 40,002 |
| 54 | 16 mm² cable-lug insulating boot – PE colourCadivi BOOT-16 | piece | 6 | 6,667 | 40,002 |
| 55 | Inverter PE cable, 1C-16 mm² Cu/XLPE/PVC, 0.6/1 kVCADIVI · Cu/XLPE/PVC · 0.6/1 kV | m | 75 | 85,985 | 6,448,875 |
| 56 | AC cable protective conduit – diameter to suit cable size and fillCVL | m | 24 | 50,036 | 1,200,864 |
| 57 | AC protective-conduit connector – to match conduit diameterCVL | set | 6 | 20,001 | 120,006 |
| 60 | String labels and DC/AC warning labels | piece | 48 | 5,001 | 240,048 |
| 61 | DC/AC cable glands for inverters and switchboards | piece | 25 | 50,038 | 1,250,950 |
| 63 | Main-route copper PE cable lugs and insulating boots, 35 mm²MAIN-PE-LUG-BOOT-35 | piece | 2 | 21,390 | 42,780 |
| 134 | Copper inverter-neutral cable lug, 16 mm²CU-LUG-16 | piece | 6 | 11,112 | 66,672 |
| 135 | Inverter neutral cable-lug insulating boot, 16 mm²BOOT-N-16 | piece | 6 | 6,667 | 40,002 |
| CABLE TRAYS / LADDERS / WALKWAYS | |||||
| 64 | Cable tray, 100 × 50 × 1.5 mm, including cover, connectors and bolts | m | 34.8 | 215,401 | 7,495,955 |
| 65 | Galvanised cable tray, 200x75x1.5 mm, including cover and connectors | m | 14.5 | 430,430 | 6,241,235 |
| 66 | Galvanised cable tray, 400x75x1.5 mm, including cover and connectors | m | 8.7 | 777,445 | 6,763,772 |
| 67 | AC cable-tray/ladder route – dimensions pending cable arrangement | m | 110 | 819,779 | 90,175,690 |
| 78 | Self-drilling screws with umbrella nuts, 2.5 cm long, fixing platforms and trays to aluminium rails | con | 360 | 1,787 | 643,320 |
| 79 | Walkway/access platform, 360 mm wide, 1.5 mm galvanised steel | m | 60 | 547,732 | 32,863,920 |
| 81 | Cable-tray supports, threaded rods and purlin clamps | set | 86 | 144,082 | 12,391,052 |
| 84 | Walkway/platform supports | set | 41 | 101,483 | 4,160,803 |
| 85 | Walkway/platform splices and connection accessories | set | 24 | 77,481 | 1,859,544 |
| 144 | Additional cable-tray/ladder accessories pending route take-offAccessories follow the actual routes. Confirm the detailed list. | lot | 1 | 10,209,381 | 10,209,381 |
| EARTHING | |||||
| 143 | Additional earthing/equipotential-bonding scope pending survey and designIndicative scope. Earthing quantities and the solution require confirmation after the survey. | lot | 1 | 4,051,281 | 4,051,281 |
| LABOUR AND INSTALLATION EQUIPMENT | |||||
| 111 | Labour for frames, modules, access platforms, cable trays and mechanical structures | person-hour | 319 | 110,279 | 35,179,001 |
| 112 | Labour for cable installation, electrical terminations and earthing | person-hour | 130 | 120,801 | 15,704,130 |
| 113 | Roof lifting equipment | shift | 1 | 7,562,932 | 7,562,932 |
| 114 | Freight and delivery | trip | 1 | 6,293,703 | 6,293,703 |
| 136 | Site technical management and supervisionQuangAnhcons | engineer-day | 23 | 1,557,898 | 35,831,654 |
| 137 | Safety supervision for work at heightQuangAnhcons | person-day | 23 | 1,091,550 | 25,105,650 |
| 138 | Mobilisation, site organisation and clearanceQuangAnhcons | visit | 1 | 6,864,427 | 6,864,427 |
| DOCUMENTATION / REGULATORY WORK / TESTING | |||||
| 115 | Review of input documents, Solar project procedures and connection checklistEPC scope as listed. Third-party inspection/review fees are confirmed separately. | engineer-hour | 10 | 313,278 | 3,132,780 |
| 116 | Roof-structure survey/document review and coordination of existing-condition images/layoutsEPC scope as listed. Third-party inspection/review fees are confirmed separately. | engineer-hour | 32 | 314,991 | 10,079,712 |
| 117 | Preliminary engineering/SLD/layout, installation method, occupational safety and QA/QCEPC scope as listed. Third-party inspection/review fees are confirmed separately. | engineer-hour | 29 | 314,757 | 9,127,953 |
| 118 | Testing, commissioning, internal acceptance and as-built/handover documentationEPC scope as listed. Third-party inspection/review fees are confirmed separately. | engineer-hour | 32 | 276,929 | 8,861,728 |
| Total before VAT | 1,205,760,000 | ||||
| Provisional VAT 10% | 120,576,000 | ||||
| Total including VAT | 1,326,336,000 | ||||
Scope: Cliplock metal roofing, 3-phase supply. Base pricing includes modules, grid-connected inverters, ordinary module rails/clamps/feet and the listed materials and installation, assuming the existing structure is suitable. Elevated frames, foundations, reinforcement, BESS and a new substation are included only when selected and priced separately.
Items requiring confirmation/outside scope: Only priced items are included. Structural assessment, approved design documents, grid-connection approval, construction/land procedures and any additional fire-protection systems must be defined for the individual project.
Preliminary quantities and unit prices for the selected scope, using the supplied parameters. Confirm layout, quantities, specifications and prices after the survey.
Formulas, substituted values and results
The calculations below use the configuration in the estimate. Checks with missing inputs are identified for completion during the survey. Preliminary results do not replace an approved design.
1. DC capacity
2. Nominal AC capacity
3. DC/AC ratio
4. Module area
5. Module mass
6. PV dead load over the module area
View all 34 calculations and items awaiting data
7. Ponding load
8. Rainwater drainage
9. Outlet count for the entered drainage capacity
10. Water per cleaning cycle
11. Cleaning-water flow rate
12. Cold-string Voc
13. Hot-string Vmp
14. DC cable length per polarity
15. DC voltage drop
16. AC branch – Iz
17. AC branch – voltage drop
18. Main AC route – Iz
19. Main AC route – voltage drop
20. Installation-phase person-hours
21. Electrical person-hours
22. Installation-phase working days
23. Electrical working days
24. AC overload protection
25. PE thermal withstand
26. Logger count by control domain
27. Module upper-edge elevation above ground
28. Frame and reinforcement steel mass
29. Base and foundation mass
30. Wind, anchor and structural-capacity checks
31. Horizontal projection of the modules
32. Installation person-hours including additional scope
33. Module mass per module area
34. Ancillary area and clearances
Indicative implementation schedule
58 working days for the baseline, including 23 days of site activities. Day 1 starts when scope and implementation conditions are agreed. These are working days, not calendar days.
Calendar: Monday-Saturday, Sundays off; public holidays and power-outage schedules are not deducted; 8 hours/day. Conservative FS relationships place mechanical work before electrical work. Phased work across roofs, multi-project resources and actual delivery delays are not modelled. Mobilisation/clearance labour is included in site organisation and is not allocated in detail.
| WBS | Task | Working days | Start | Finish | Predecessors (FS) | Planned resources | Timeline: day 1 → 58 |
|---|---|---|---|---|---|---|---|
| 1 | Survey, scope confirmation and roof data | 2 | Day 1 | Day 2 | — | 2 people | |
| 2 | Design, coordination and material approval | 3 | Day 3 | Day 5 | 1 | 2 people | |
| 3 | Awaiting grid-connection / owner confirmation | 20 | Day 6 | Day 25 | 2 | As defined in the scope/package | |
| 4 | Procurement, fabrication and delivery | 30 | Day 6 | Day 35 | 2 | As defined in the scope/package | |
| 5 | Mobilisation and site preparation | 2 | Day 36 | Day 37 | 3, 4 | As defined in the scope/package | |
| 6 | Frames, modules, cable trays and walkways | 7 | Day 38 | Day 44 | 5 | 6 people | |
| 7 | Cable installation, terminations, switchboards and earthing | 9 | Day 45 | Day 53 | 6 | 2 people | |
| 8 | Testing, commissioning and acceptance | 2 | Day 54 | Day 55 | 7 | 2 people | |
| 9 | As-built records, handover and site clearance | 3 | Day 56 | Day 58 | 8 | As defined in the scope/package |
Brown: tasks on the baseline critical path. Green: tasks with float. FS means the preceding task finishes before the next starts.
CPM follows the baseline finish-to-start relationships. Multi-project resource levelling and import into Microsoft Project have not been verified.
Generation and self-consumption simulation for the 100 kWp example
Supplementary simulation, separate from the Solar 8.21.0 estimate results. Illustrative Ho Chi Minh City coordinates (10.8231°N; 106.6297°E), not a completed project’s location. The model uses 8,760 hours of historical ERA5 weather for 2023 through PVGIS 5.3. Demand is assumed; these are not meter readings, a forecast or a guarantee.
Installed PV array 100.48 kWp DC; AC limit 90.00 kW. PVGIS model: generic crystalline silicon, tilt 10°, south-facing (aspect 0°), system loss 14% and assumed rear ventilation. This scenario has no BESS and no grid export. Surplus generation is curtailed and export revenue is 0.
PV supplies 44.0% of total scenario demand. Energy lost to the AC cap in these hourly averages is 0.00 kWh. A result of 0 does not exclude shorter-than-hourly peaks.
Monthly energy
| Month (UTC) | Plane-of-array irradiance kWh/m² | Available PV kWh | Direct PV consumption kWh | Curtailed PV surplus kWh | Download assumptions kWh | Grid import kWh |
|---|---|---|---|---|---|---|
| T1 | 145.3 | 10,857 | 9,406 | 1,450 | 23,736 | 14,330 |
| T2 | 171.8 | 12,660 | 10,878 | 1,782 | 21,792 | 10,914 |
| T3 | 202.6 | 14,790 | 12,868 | 1,922 | 24,420 | 11,552 |
| T4 | 181.4 | 13,330 | 11,411 | 1,919 | 22,860 | 11,449 |
| T5 | 166.2 | 12,298 | 11,154 | 1,145 | 24,420 | 13,266 |
| T6 | 142.4 | 10,645 | 9,577 | 1,068 | 23,544 | 13,967 |
| T7 | 133.0 | 9,976 | 8,997 | 979 | 23,736 | 14,739 |
| T8 | 164.8 | 12,426 | 11,096 | 1,330 | 24,420 | 13,324 |
| T9 | 134.4 | 10,080 | 9,170 | 910 | 23,544 | 14,374 |
| T10 | 150.2 | 11,162 | 9,814 | 1,348 | 23,736 | 13,922 |
| T11 | 147.7 | 10,990 | 9,667 | 1,323 | 23,544 | 13,877 |
| T12 | 162.5 | 12,031 | 10,578 | 1,453 | 23,736 | 13,158 |
Representative daily curve
The curve averages 365 samples for each Vietnam-time hour (UTC+7). Self-consumption is calculated hourly before averaging. Taking the minimum of two average curves is not a substitute for the 8,760-hour simulation.
Assumed demand used in the calculation
Illustrative industrial operation Monday-Saturday: 8.00 kW base load and 80.00 kW during main working hours. Sunday stays at base load. Public holidays and shutdowns are not modelled.
View all 24 assumed demand hours
| Vietnam local time | Monday-Saturday (kW) | Sunday (kW) |
|---|---|---|
| 00:00–01:00 | 8.000 | 8.000 |
| 01:00–02:00 | 8.000 | 8.000 |
| 02:00–03:00 | 8.000 | 8.000 |
| 03:00–04:00 | 8.000 | 8.000 |
| 04:00–05:00 | 8.000 | 8.000 |
| 05:00–06:00 | 8.000 | 8.000 |
| 06:00–07:00 | 8.000 | 8.000 |
| 07:00–08:00 | 30.000 | 8.000 |
| 08:00–09:00 | 80.000 | 8.000 |
| 09:00–10:00 | 80.000 | 8.000 |
| 10:00–11:00 | 80.000 | 8.000 |
| 11:00–12:00 | 80.000 | 8.000 |
| 12:00–13:00 | 55.000 | 8.000 |
| 13:00–14:00 | 80.000 | 8.000 |
| 14:00–15:00 | 80.000 | 8.000 |
| 15:00–16:00 | 80.000 | 8.000 |
| 16:00–17:00 | 80.000 | 8.000 |
| 17:00–18:00 | 40.000 | 8.000 |
| 18:00–19:00 | 15.000 | 8.000 |
| 19:00–20:00 | 8.000 | 8.000 |
| 20:00–21:00 | 8.000 | 8.000 |
| 21:00–22:00 | 8.000 | 8.000 |
| 22:00–23:00 | 8.000 | 8.000 |
| 23:00–24:00 | 8.000 | 8.000 |
These are not survey data, meter readings or mandatory allowances. Replace the assumed demand with actual data before assessing a customer’s project.
Simulation formulas, substituted values and results
Example using the hour with the highest available PV in the dataset: 2023-03-15T11:30:00+07:00 (mid-hour timestamp).
| PV power before the AC limit | Pscaled,h = PPVGIS,h / 1,000 × PDC 741.51 / 1,000 × 100.48 74.5069 kW |
|---|---|
| Available PV after AC limiting | Pavail,h = min(Pscaled,h; PAC) min(74.5069; 90.00) 74.5069 kW |
| Assumed demand in the example hour | Pload,h = Pnominal × mh 100 × 0.80 80.0000 kW |
| Direct PV consumption | Pself,h = min(Pavail,h; Pload,h) min(74.5069; 80.0000) 74.5069 kW |
| PV surplus to be curtailed under zero export | Pcurtail,h = max(Pavail,h − Pload,h; 0) max(74.5069 − 80.0000; 0) 0.0000 kW |
| Grid import power | Pgrid,h = max(Pload,h − Pavail,h; 0) max(80.0000 − 74.5069; 0) 5.4931 kW |
| Available PV energy over the full 8,760-hour window | Eavail = Σ(Pavail,h × Δt), Δt = 1 hour Σ h=1…8,760 [100.48 × PPVGIS,h/1,000, capped at 90.00 kW] × 1 hour 141245.35 kWh |
| PV self-consumption ratio | SCR = Eself / Eavail × 100% 124616.86 / 141245.35 × 100% 88.23% |
| Demand coverage by PV | SSR = Eself / Eload × 100% 124616.86 / 283488.00 × 100% 43.96% |
Sources, scope and model limitations
- Ho Chi Minh City is an illustrative location for comparison, not the address of a surveyed project or customer.
- ERA5 weather for 2023 is historical gridded reanalysis; PV output is modelled. It is not meter data, a typical meteorological year, a future forecast or a generation guarantee.
- PVGIS v5.3 is pinned for reproducibility. PVGIS 6 has update 19 Oct 2026; do not describe v5.3 as the latest API version.
- crystSi is a generic crystalline-silicon technology model, not a set of curves calibrated specifically for the LONGi modules or Sungrow inverters in this estimate.
- The 14% system loss is a PVGIS input already included in the exported power. Do not deduct another 14% or apply inverter efficiency for a second time.
- The mountingplace=free setting assumes rear ventilation. The actual roof may run hotter. Nearby shading, seasonal soiling, downtime, individual degradation and each inverter’s MPPT/voltage/current limits are not modelled.
- The AC limit is applied as a minimum against the estimate’s total nominal AC rating. Hourly averages may miss clipping or limit exceedances lasting less than one hour.
- Self-consumption and surplus use assumed hourly demand. Replace this with at least 15-60-minute meter data to assess a specific customer’s site.
- Scenario without BESS or grid export, assuming ideal curtailment control. Curtailed surplus is not saleable energy; surplus-sale revenue is 0. Actual zero-export or backup performance is not confirmed.
- Monthly totals follow the source data’s UTC calendar months. Demand and daily charts use Vietnam time UTC+7. The full window is 01 Jan 2023 00:00-01 Jan 2024 00:00 UTC, corresponding to 01 Jan 2023 07:00-01 Jan 2024 07:00 in Vietnam.
- The daily curve averages the same time slot over 365 days in the data window. It is not the curve for a specific sunny day. Self-consumption is calculated hourly before averaging.
- This supplement does not calculate tariffs, savings, payback, interest or revenue from surplus electricity.
Source demand data downloaded 02 Nov 2026; SHA-256: a1955aa9013eedf69f2dd59272d8fde92bd98abe43259e211f2026fb2b74601f. Simulation version: qac-solar-energy-supplement/1.0.0.
Download simulation data and assumptions (.zip)
Standards, regulations and actions for this configuration
The references were checked as of 02 Nov 2026. They include Decree 58/2025, as amended by Decree 243/2026, current electrical-safety regulations and fire-safety requirements for the building type. Applicable procedures depend on the connection diagram, responsible entity and operating mode; they cannot be inferred solely from the capacity label or inverter voltage. Selected standards and mandatory regulations have different scopes. This is a pre-survey reference configuration, not confirmation of compliance at a specific site.
| Legislation/standard | Applicability to this estimate |
|---|---|
| Decree 58/2025/ND-CP, as amended by Decree 243/2026/ND-CP | Identify self-generation/self-consumption arrangements and procedures for the project, responsible entity and connection point. |
| Decree 243/2026/ND-CP | Surplus-electricity provisions and related amendments. This self-consumption estimate does not assume revenue from surplus sales. |
| QCVN 25:2025/BCT; Circular 41/2025/TT-BCT | Electrical safety. Check the actual work and operating scope. |
| Decree 105/2025/ND-CP, as amended by Decree 347/2026/ND-CP | Fire-safety duties depend on building type and alterations. Storage requires a separate assessment. |
| QCVN 06:2022/BXD and Amendment 1:2023 | Fire safety for buildings and structures. Check the building type and the scope of alterations. |
| TCVN 7447-7-712:2019 | Low-voltage PV electrical installations. |
| IEC 60364-7-712:2025 | Check PV installation design against the selected edition. |
| IEC 62548-1:2023 + AMD1:2025 | PV-array design, DC wiring, protection and earthing; it does not replace the complete BESS design. |
| TCVN 11855-1:2017 | PV documentation, inspection and testing within the standard’s scope. |
| TCVN 2737:2023 | Loading, wind and load combinations. Roofs, anchors and structures require a separate survey and calculation. |
Before implementation, finalise the connection diagram, roof/anchor/wind checks, protection coordination, fire-safety scope and applicable notification/registration or other procedures. A list of standards alone does not certify that the configuration meets every requirement of a particular project.
Read the connection and surplus-electricity sale conditions.
Acceptance, warranty and operation
Handover documents should include the equipment configuration, as-built drawings, polarity and insulation checks, earthing results, protection/control tests, monitoring settings and operating instructions for the agreed scope. Test export limitation and loss-of-grid operation against the design. Systems with batteries also require BMS/EMS, protection, transfer and supplied-load checks.
Equipment warranty periods follow the exact models, documents and manufacturer policies at supply. Confirm installation warranty, maintenance, cleaning and fault-response arrangements in the contract. Do not apply one warranty period to every component.
Send roof information and survey requirementsRecalculate using your parameters
Solar installation images

Compare configurations and learn more
Estimate another Solar system
Use the Solar calculator to compare configurations, preliminary EPC prices and other storage options.
Learn more Solar calculator, BESS calculator or substation prices on the dedicated page.